TEST # 1

SCHEDULING II

The following information is given for the project “Building Design”:
 

Activity
Department
Resource
Cost/Unit time
Following Activity
Design building
Engineering
Design eng. 240 hrs
40
Review and Approve
Review and Approve
Engineering
Prog. Manager 40 hrs.
25
Assemble tech Data
Assemble tech Data
Engineering
Prog. Manager 80 hrs.
25
Rev. Bids & Rev. Technical
Rev. Bids
Purchasing
Account. 16 hrs.
20
Prepare and Solic. Bids
Rev. Technical
Purchasing
Account. 8 hrs.
20
Prepare and Solic. Bids
Prepare and Solic. Bids
Purchasing
Account. 24 hrs.
20
Fabricate & Deliver
Fabricate & Deliver
Construction
Equip. 1 unit/day 30 days

 
240

 
Laborers 10/day 30days
100

a) Prepare a bar chart and create the on-screen Pert view
b) Prepare a cost account dictionary with the following information and assign one account to each activity
 
Account #
Account Title
1000
Design
1001
Accounting
1002
Construction

c)  Define the equipment as a driving resource
d)  Modify the timescale, increasing its density
e)  Create the on-screen resource profiles
f)   Create the on-screen resource table
g)  Create the on-screen cost profiles
h)  Create the on-screen cost table
i)  Assign a calendar of seven days workweek to the construction department activity and a calendar of five days workweek to al  the other activities
j)  Create a work breakdown dictionary, with two levels.