1. The network shown represents a project. The owner wants to finish as soon as possible, but his budget for this project is only $9 000. All the activities have been crashed, giving a project duration of 17 days at a cost of 10 000 units. Find the minimum project duration under the imposed cost restriction.
2. Carry out optimal compression of a simple network of three activities
having the following utility data.
Activity 1 - 2 1 - 3 2 - 3
tn 15 27 9
Cn 1000 1800 2000
tc 5 15 5
Cc 1400 4200 2120
Nature of cost curve continuous continuous discrete point