A contractor has divided a project into 8 activities. He has determined the following information:
Activity A takes 5 days and can be done initially
Activity B takes 6 days and can be done initially
Activity C takes 8 days and follows activities A and B
Activity D takes 5 days and follows activity C
Activity E takes 7 days and follows activity A and B
Activity F takes 10 days and follows activity B
Activity G takes 4 days and follows activities F and E
Activity H takes 2 days and follows activities D and G
a) Draw a CPM network for the project indicating the critical path
b) Prepare a bar chart for the project indicating the predecessors and successors activities
c) Find the total float for each activity
d) Find the free float for each activity