Complete the forward pass, backward pass and float calculations for the project represented by the figure. Also complete the tabular informatio for the shown table.
Activity | Duration (dur) | Early Start (es) | Late Start | Early Finish | Late Finish (l-fin) | Float ( fl ) |
A | ||||||
B | ||||||
C | ||||||
D | ||||||
E | ||||||
F | ||||||
G | ||||||
H | ||||||
I | ||||||
J | ||||||
K | ||||||
L | ||||||
M | ||||||
N | ||||||
O |