Scheduling 1
AUTOTEST # 2

A contractor must prepare a project plan for a project which consists of placing a large culvert. He divides the project into the following project activities:
 
 

Activity Activity Identification
Dig hole A
Obtain sub base material B
Obtain pipe C
Move pipe to site  D
Fine grade soil in hole E
Place sub base material F
Compact sub base material G
Place pipe and level it H
Remove excess sub base material from site I
Back fill with soil J
________________________________________________________________________________________________
Activity A can be done initially and takes 8 working days.
Activity B can be done initially and takes 16 working days.
Activity C can be done initially and takes 24 working days.
Activity D can be done after C and takes 2 working days.
Activity E can be done after A and takes 5 working days.
Activity F can be done after B and E and takes 4 working days.
Activity G can be done after F and takes 8 working days.
Activity H can be done after D and G and takes 6 working days.
Activity I can be done after F and takes 2 working days.
Activity J can be done after H and takes 5 working days.