Scheduling 1
AUTOTEST # 2
A contractor must prepare a project plan for a project which consists
of placing a large culvert. He divides the project into the following project
activities:
Activity |
Activity Identification |
Dig hole |
A |
Obtain sub base material |
B |
Obtain pipe |
C |
Move pipe to site |
D |
Fine grade soil in hole |
E |
Place sub base material |
F |
Compact sub base material |
G |
Place pipe and level it |
H |
Remove excess sub base material from site |
I |
Back fill with soil |
J |
________________________________________________________________________________________________
Activity A can be done initially and takes 8 working days.
Activity B can be done initially and takes 16 working days.
Activity C can be done initially and takes 24 working days.
Activity D can be done after C and takes 2 working days.
Activity E can be done after A and takes 5 working days.
Activity F can be done after B and E and takes 4 working days.
Activity G can be done after F and takes 8 working days.
Activity H can be done after D and G and takes 6 working days.
Activity I can be done after F and takes 2 working days.
Activity J can be done after H and takes 5 working days.